Issued: August 3, 2017 by:

HammerWorks Co.

Danny McGlashing
2 Ocean Ave #500
Revere, MA 02151
Expires: September 2, 2017 to:

John and Vaia Tehrani

19 Salem St
Charlestown, MA
US

Estimate

Task 1.0

Hammerworks agrees to furnish all material and labor associated with the
demolition and removal of the 3rd floor rear 2 windows at 19 Salem St and replace with Pella architectural (pine) windows (interior to be painted white to match existing windows) with charcoal finished storm and screen exterior attachments and brushed bronze finished hardware at the request of the client. The exterior trim will be replaced with high end Azek pvc trim and painted black to match the buildings exterior trim elements. Interior window casings are original to the house and have a unique architectural element to them and will be preserved, reinstalled and painted to match the clients existing interior trim.

Rate

$4,200

Qty

1

%

0%

Amount

$4,200

Yet to be Approved

Terms & Conditions

HammerWorks agrees to complete all work mentioned in this estimate within 2-7 business days of the the jobs commencement (pending the weather). If this estimate is accepted, a start date convenient for both the client and HammwerWorks will be agreed upon. Payment(s) totaling $4200 are to be paid as follows; the first payment is to be made payable by check to HammerWorks upon acceptance of this estimate in the amount of $3200. A second and final payment of $1000 is to be made within 2 business days of the jobs completion.

Additional work not mentioned in this estimate is not included in this job but can be added for an additional fee via change order if requested by the client and approved by Danny McGlashing of HammerWorks.

Estimate is Expired

Estimate History

Updated 3402 days ago

Estimate updated by Danny McGlashing.

Updated 3402 days ago

Estimate updated by Danny McGlashing.

Status Update 3402 days ago

Status changed: Draft to Pending.